Our client needed to position 3 LV panels within a switch room. In order to do this, we had to pass through a door which was too low for them to fit through.

Shown here JWI used our custom made, 2T safe working load lower load to move the panels from vertical to horizontal in order to allow us to overcome the door restrictions and locate the panels into their final position.

Our method saved time and cost in erecting an A-Frame gantry and allowed us to achieve the clients goal in a safe working manner.